Bar chart, end of September 2025 vs 2026: GE Vernova turbine orders 62 GW to 122 GW; Vertiv advance payments $1.1B to $4.1B.

Chips are still short. Now power is, too.

posted in: AI Buildout, Blog | 0

ASML says its planned supply of chip-making machines won’t fully meet demand in 2027 or 2028. Gas turbines on order or reserved at GE Vernova nearly doubled in a year, to 122 gigawatts, and customers have paid power and cooling maker Vertiv $4.1B in advance, 3.6 times a year earlier.

The gear bill per megawatt is rising too: Vertiv now estimates it can sell $3.25–3.75M for each megawatt of data-center capacity, up 10–15% from its earlier range. A chip without power earns nothing, so returns depend on megawatts secured, not chips bought.

Strategist is built to put an independent strategy beside management’s, so a plan that counts chips but not megawatts stands out.

Which one limits your plan? strategist.intelligenxe.com

Follow INTELLIGENXE:

INTELLIGENXE has developed Strategist, an agentic AI platform built to generate an independent, auditable corporate strategy for any publicly traded company and benchmark management’s current strategy against it — “a second opinion at scale.”

Comments are closed.